QUESTION

CSAT

Medium

Maths

Prelims 2024

A certain number of men can complete a piece of work in 6k6k days, where kk is a natural number. By what percent should the number of men be increased so that the work can be completed in 5k5k days?

Select an option to attempt

Explanation

Let the number of men required to complete the work in 6k6k days be denoted by mm. According to the problem, this number of men can complete the work in 6k6k days.

The relationship between the number of men and the time taken to complete the work can be described by the formula:

Men × Time = Work (constant)

So, initially:

m×6k=m \times 6k = constant work

Let the new number of men be nn. According to the formula, for the work to be completed in 5k5k days:

n×5k=n \times 5k = constant work

Since the work is constant, we can equate the two expressions for the work:

m×6k=n×5km \times 6k = n \times 5k

Simplifying this:

n=65×mn = \frac{6}{5} \times m Percent increase =(nm)/m×100=((65)mm)/m×100=(15)×100=20%= (n - m) / m \times 100 = ((\frac{6}{5})m - m) / m \times 100 = (\frac{1}{5}) \times 100 = 20\%

Thus, the number of men should be increased by 20%20\% to complete the work in 5k5k days.

Trusted by 2L aspirants

Practice UPSC Prelims PYQs Smarter

Practice Now
  • Track accuracy & weak areas
  • See past trends & repeated themes
Start Practicing Now

Crack UPSC with your
Personal AI Mentor

An AI-powered ecosystem to learn, practice, and evaluate with discipline

SuperKalam is your personal mentor for UPSC preparation, guiding you at every step of the exam journey.

Download the App

Get it on Google PlayDownload on the App Store
Follow us

ⓒ Snapstack Technologies Private Limited