A, B, C working independently can do a piece of work in 8, 16 and 12 days respectively. A alone works on Monday, B alone works on Tuesday, C alone works on Wednesday; A alone, again works on Thursday and so on. consider the following statements:

  1. The work will be finished on Thursday.
  2. The work will be finished in 10 days.

Which of the above statements is/are correct?

Select an option to attempt

Explanation

A, B, C working independently can do a piece of work in 8, 16 and 12 days respectively.

Let the total amount of work be LCM (8,16,12)=48(8, 16, 12) = 48 units

So, Efficiency of A = 48/8=648/8 = 6 units/day

Efficiency of B = 48/16=348/16 = 3 units/day

Efficiency of C = 48/12=448/12 = 4 units/day

The amount of work done in 3 days (Monday + Tuesday + Wednesday) = 6+3+4=136 + 3 + 4 = 13 units Thereafter, the amount of work done in subsequent 3 days (Thursday + Friday + Saturday) = 6+3+4=136 + 3 + 4 = 13 units

Thereafter, the amount of work done in subsequent 3 days (Sunday + Monday + Tuesday) = 6+3+4=136 + 3 + 4 = 13 units

Thereafter, the amount of work done in subsequent 2 days (Wednesday + Thursday) = 6+3=96 + 3 = 9 units

So, amount of work done in 11 days = 13+13+13+9=4813 + 13 + 13 + 9 = 48 units

So, work will get finished in 11 days on Thursday. It means that Statement 1 is correct, but Statement 2 is incorrect.

Hence, option A is correct.

Trusted by 2L aspirants

Practice UPSC Prelims PYQs Smarter

Practice Now
  • Track accuracy & weak areas
  • See past trends & repeated themes
Start Practicing Now

Crack UPSC with your
Personal AI Mentor

An AI-powered ecosystem to learn, practice, and evaluate with discipline

SuperKalam is your personal mentor for UPSC preparation, guiding you at every step of the exam journey.

Download the App

Get it on Google PlayDownload on the App Store
Follow us

ⓒ Snapstack Technologies Private Limited