Pumped hydro project near Malshej Ghat gets approval for impact studies, Pg8

Malshej Ghat's 1,200-MW pumped hydro project secures preliminary approval for environmental impact studies amidst ecological concerns and Western Ghats fragility.

Practice MCQs

775 Students attempted
Attempt Now

Key Highlights:

  • THDC India Ltd's 1,200-MW pumped hydro project near Malshej Ghat received preliminary approval for environmental impact assessment (EIA) studies.
  • The project, estimated to cost ₹6,815 crore, is located in the Kalu river valley and requires 310 hectares of land.
  • The Expert Appraisal Committee (EAC) directed THDC to submit water utilization mapping and obtain hydrological clearances.
  • The project uses a closed-loop system and is located 3 km from the Kalsubai Harishchandragad wildlife sanctuary.

Detailed Insights:

  • The project site includes villages listed as eco-sensitive areas in the Centre’s 2024 draft notification on protection of Western Ghats.
  • The pumped hydro project will use a 28-31 m high dam for the upper reservoir and initially draw water from the Kalu River to fill the lower reservoir.
  • Pumped storage involves pumping water between two reservoirs at different elevations to generate electricity during high demand.
  • The EAC has directed developers to obtain hydrological clearances from the Central Water Commission and state government due to other projects drawing water from the Kalu river.
  • The EAC has advised THDC to ensure that small rivulets feeding water into the Kalu river are not disturbed during project establishment.
  • A sub-committee will visit the project site before environmental clearance, given its location in the ecologically fragile Western Ghats.
  • The central government is promoting pumped hydro generation to achieve its net-zero plans and generate 500 GW of non-fossil-based power.

Key Concepts Involved:

  • Environmental Impact Assessment (EIA): A process to evaluate the environmental consequences of a proposed project or policy.
  • Pumped Hydro Storage: A type of hydroelectric energy storage system used for load balancing.
  • Closed-loop System: A system where water is recycled within the project without continuous draw from a river.
SuperKalam
SuperKalam is your personal mentor for UPSC preparation, guiding you at every step of the exam journey.

Download the App

Get it on Google PlayDownload on the App Store
Follow us

ⓒ Snapstack Technologies Private Limited