‘Transmission Constraints Threaten India’s Renewable Energy Expansion’, Pg12
ICRA warns inadequate transmission infrastructure and grid congestion threaten India's ambitious renewable energy targets, causing project curtailment and slowing new bids.
Insufficient transmission lines are significantly impeding India's renewable energy expansion, leading to the curtailment of solar power projects.
Rating agency ICRA reported that approximately 37% of renewable energy capacity operating under Temporary General Network Access (T-GNA) faces 30-50% curtailment during daylight hours.
Peak curtailment reached 8,617 MW in Western India and 5,573 MW in the Northern region as of August 6.
Timely development of intra-State and inter-State transmission infrastructure, alongside increased storage capacity, is crucial for sustaining renewable energy growth.
India currently has over 150 GW of renewable projects under construction as of June 30, with renewable energy projected to account for over 35% of electricity generation by FY2029-30.
Detailed Insights:
Curtailment occurs when a power generator is forced to reduce or stop electricity production due to oversupply or grid congestion.
T-GNA is a short-term arrangement allowing renewable energy projects to use available capacity on the inter-State transmission system for periods up to 11 months.
Prolonged use of T-GNA and subsequent curtailment negatively impacts the revenues and operational costs of power suppliers.
Other challenges hindering renewable energy expansion include delays in Power Purchase Agreements (PPAs), land acquisition, and financial issues of distribution companies.
Bids for new renewable energy projects have seen a sharp decline, from 40.6 GW in 2024-25 to 4.7 GW by August 10 this year.
The focus in new bidding processes is shifting towards Firm and Dispatchable Renewable Energy (FDRE) and Round-the-Clock (RTC) power to ensure grid stability.
The National Grid of India, managed by Power Grid Corporation of India Limited (PGCIL), is the high-voltage transmission network connecting power stations and substations across the country.
Key Concepts Involved:
Curtailment: The intentional reduction of electricity output from power generators, typically renewables, to maintain grid balance due to oversupply or transmission constraints.
Temporary General Network Access (T-GNA): A short-term contractual arrangement allowing power generators to utilize existing inter-State transmission capacity.
Power Purchase Agreements (PPAs): Long-term contracts between electricity generators and buyers for the sale and purchase of power.
Firm and Dispatchable Renewable Energy (FDRE): Renewable energy that can be supplied reliably and on demand, often achieved through hybrid projects or energy storage.
Round-the-Clock (RTC) Power: Continuous electricity supply available 24 hours a day, typically by combining various energy sources and storage solutions.